Our Case: “The Heart of Harmony”
The ‘Heart of Harmony’ Community Center
A PMP Case Study in Action
Project Vitals
Key metrics that define the foundation of the “Heart of Harmony” project in Mahres, Tunisia.
Total Project Budget
18M
TND
Project Timeline
2.5 Years
(Aug 2025 – Jan 2028)
Funding Sources
Project Timeline & Milestones
A high-level overview of the major phases and critical milestones for the project.
1
Aug 2025
Project Kick-off & Initiation
2
Mar 2026
Final Design Approval & Permits Acquired
3
Jun 2026
Groundbreaking Ceremony
4
Nov 2027
Construction Completion
5
Jan 2028
Grand Opening
Scope Breakdown
A visualization of the major Work Breakdown Structure (WBS) components, representing the key areas of project effort.
🏗️ Building Construction
The largest component, covering the physical structure, interiors, and MEP systems.
✍️ Design & Permitting
Includes all architectural design, engineering, and securing regulatory approvals.
🤝 Procurement & Management
Covers contract management, vendor selection, and overall project management efforts.
🌳 Exterior & Site Work
Encompasses landscaping, parking, and site preparation.
Stakeholder Landscape
Visualizing the power and interest of key stakeholders to guide our engagement strategy. Bubble size indicates influence.
Performance Snapshot (EVM)
A hypothetical Earned Value Management scenario at the 12-month mark, providing a clear view of project health.
Cost Performance (CPI)
0.91
Over Budget
Schedule Performance (SPI)
0.83
Behind Schedule
Cost Variance (CV)
-500k
TND
Schedule Variance (SV)
-1M
TND