Earned Value Management (EVM) is a project management methodology that integrates scope, schedule, and cost to assess project performance and progress. It provides an objective way to measure project performance and forecast future performance.
Formula: PV = Budget at Completion (BAC) × % Planned Complete
Example: A project has a total budget (BAC) of $100,000. By the end of the first month, 20% of the work was planned to be completed.
PV = $100,000 × 0.20 = $20,000
Formula: EV = Budget at Completion (BAC) × % Actual Complete
Example: For the same project with a BAC of $100,000, if 15% of the work is actually completed.
EV = $100,000 × 0.15 = $15,000
Example: For the 15% of work actually completed, the actual cost incurred was $18,000. AC = $18,000
Formula: CV = EV – AC
Interpretation:
CV > 0 : Under budget (favorable)
CV < 0 : Over budget (unfavorable)
CV = 0 : On budget
Example: Using the values above: CV = $15,000 (EV) – $18,000 (AC) = -$3,000
Interpretation: The project is $3,000 over budget.
Formula: SV = EV – PV
Interpretation:
SV > 0 : Ahead of schedule (favorable)
SV < 0 : Behind schedule (unfavorable)
SV = 0 : On schedule
Example: Using the values above: SV = $15,000 (EV) – $20,000 (PV) = -$5,000
Interpretation: The project is $5,000 behind schedule.
Formula: CPI = EV / AC
Interpretation:
CPI > 1 : Performing efficiently (under budget)
CPI < 1 : Performing inefficiently (over budget)
CPI = 1 : Performing on budget
Example: Using the values above: CPI = $15,000 (EV) / $18,000 (AC) = 0.83
Interpretation: For every dollar spent, only $0.83 worth of work was earned. The project is performing inefficiently in terms of cost.
Formula: SPI = EV / PV
Interpretation:
SPI > 1 : Performing efficiently (ahead of schedule)
SPI < 1 : Performing inefficiently (behind schedule)
SPI = 1 : Performing on schedule
Example: Using the values above: SPI = $15,000 (EV) / $20,000 (PV) = 0.75
Interpretation: The project is progressing at 75% of the planned rate. The project is performing inefficiently in terms of schedule.
This is the total value of the project baseline.
Example: The total budget for the entire project is $100,000. BAC = $100,000
There are several ways to calculate EAC, depending on assumptions about future performance:
This assumes that the current cost efficiency will continue.
Formula: EAC = BAC / CPI
Example: Using BAC = $100,000 and CPI = 0.83: EAC = $100,000 / 0.83 = $120,481.93 Interpretation: At the current rate of spending, the project is expected to cost approximately $120,481.93 to complete.
This assumes that past cost variances are atypical and future work will be completed as planned.
Formula: EAC = AC + (BAC – EV)
Example: Using AC = $18,000, BAC = $100,000, EV = $15,000: EAC = $18,000 + ($100,000 – $15,000) = $18,000 + $85,000 = $103,000
Interpretation: If future work is performed at the budgeted rate, the project is expected to cost $103,000 to complete.
This is a more complex formula that considers both cost and schedule efficiency.
Formula: EAC = AC + (BAC – EV) / (CPI × SPI)
Example: Using AC = $18,000, BAC = $100,000, EV = $15,000, CPI = 0.83, SPI = 0.75:
EAC = $18,000 + ($100,000 – $15,000) / (0.83 × 0.75) = $18,000 + $85,000 / 0.6225 = $18,000 +
$136,546.18 = $154,546.18
Interpretation: Considering both cost and schedule efficiency, the project is expected to cost approximately
$154,546.18 to complete.
Formula: EAC = AC + ETC
Example: If a new estimate to complete the remaining work (ETC) is $90,000: EAC = $18,000 (AC) + $90,000 (ETC) = $108,000
Interpretation: Based on the new estimate for remaining work, the project is expected to cost $108,000 to complete.
Formula: ETC = EAC – AC (based on the chosen EAC calculation)
Example: Using EAC = $120,481.93 (from EAC = BAC/CPI) and AC = $18,000:
ETC = $120,481.93 – $18,000 = $102,481.93
Interpretation: The remaining work is expected to cost $102,481.93.
Formula: ETC = (BAC – EV) / CPI
Example: Using BAC = $100,000, EV = $15,000, CPI = 0.83: ETC = ($100,000 – $15,000) / 0.83 = $85,000 / 0.83 = $102,409.64
Interpretation: The remaining work is expected to cost $102,409.64, assuming current cost efficiency.
Formula: VAC = BAC – EAC
Example: Using BAC = $100,000 and EAC = $120,481.93: VAC = $100,000 – $120,481.93 = -$20,481.93
Interpretation: The project is expected to be $20,481.93 over budget at completion.
TCPI (to meet BAC): This indicates the efficiency needed to finish the project within the original budget.
Formula: TCPI_BAC = (BAC – EV) / (BAC – AC)
Example: Using BAC = $100,000, EV = $15,000, AC = $18,000:
TCPI_BAC = ($100,000 – $15,000) / ($100,000 – $18,000) = $85,000 / $82,000 = 1.036
Interpretation: To finish within the original budget, the remaining work must be completed at an efficiency of 1.036. This means for every dollar spent, $1.036 worth of work must be earned.
Formula: TCPI_EAC = (BAC – EV) / (EAC – AC)
Example: Using BAC = $100,000, EV = $15,000, EAC = $120,481.93, AC = $18,000:
TCPI_EAC = ($100,000 – $15,000) / ($120,481.93 – $18,000) = $85,000 / $102,481.93 = 0.829
Interpretation: To finish within the current EAC, the remaining work must be completed at an efficiency of 0.829. This means for every dollar spent, $0.829 worth of work must be earned.
Not a member yet? Register now
Are you a member? Login now